Project details

NAFTAL

Client: NAFTAL
When: 2013 – 2015
Where: Mostaganem, ALGERIE
Type of contract: EPC

Technical file

  • LPG pump
  • Truck loading stations
  • LPG, fire and air network
  • 600 bottles / h LPG cylinder filling line
  • Gas and flame detection
  • Center supervision and automation

Key elements

  • No downtime
  • Strict compliance with quality procedures and safety rules
  • Duration of the work: 12 months

An in-depth risk analysis for the renovation

NAFTAL

Initiated in 2013 on the basis of a well-rounded specifications, the studies made it possible to define quickly the necessary and worrying equipment in terms of delivery time.

To carry out this project, our teams were able to navigate the intricacies of the local authorities to validate:

  • both the studies and the equipment provided,
  • the work carried out
  • and the testing and commissioning procedures,
  • while respecting the deadline commitments.

The construction phase then extended over 12 months in close collaboration with the operator.

The work was carried out in parallel with the existing installations in order to keep the daily operations of the center up and running

The entire project and especially the construction took place in strict compliance with quality procedures and safety rules in the ATEX zones of the facility.

No incidents or work accidents were reported during the on-site construction phase.

Once tested, verified by control bodies and made by-products, the new installations were put into service and made available to the operator.

The increased experience, previously developed in the same country with this same client, made it possible to orient the procedures immediately in the right direction and save precious time on the implementation schedule.

Read more SALTA ENERGY references

Projects

On many occasions, we have provided solutions to atypical projects due to their technical or organizational complexity.