Hitia'a, French Polynesia

The construction of mounded storage depot supplied by ship

LPG TERMINALS

Building an LPG filling center starts with truly understanding the client’s needs, market constraints, and operational goals. Salta Energy meets these challenges with turnkey solutions that combine expert coordination, strict compliance with standards, long-lasting quality, cost control, and customer satisfaction.

Budget

> 5 M EUR

Year

2021 - 2024

Technical datasheet 

  • Filling of 5 kg and 10 kg composite domestic cylinders (butane)
  • Filling of 50 kg industrial steel cylinders (butane)
  • Capacity of 220 cylinders/hour
picto - stockage.png

Installations

  • 4000 T mounded Storage
  • Semi-automatic Filling Line
  • Fire Protection System
  • Utilities: Electricity and Compressed Air
  • Gauging and Detection Systems
  • Supervision and Automation System
  • Ship Connection Skid

Services

  • Basic Design / Detailed Design / Execution Design
  • Equipment Supply
  • Consolidation and Inspection
  • Packaging and Delivery
  • Supervision, Technical Management and Coordination
  • Commissioning
20240926_073750.png

Reduce costs, optimize space, support growth

The success of an LPG depot starts with solid organization and effective coordination of all stakeholders. With time differences of up to 12 hours, the challenge is real. Salta Energy knows how to strike the right balance between precision and flexibility — that’s where our experience makes the difference.

Once coordination is in place, the technical work begins. Salta Energy turns ideas into reality: 4000 T of storage, maritime transport, 300 m offshore hoses, 400 m of buried piping, and mounded tank installation. Each step is an engineering challenge, met with precise planning and complete on-site expertise.

After the design phase, logistics takes over. Salta Energy coordinates the maritime transport of all equipment, strictly following the project schedule. Each item is tracked, numbered, and quality-checked. The result: everything arrives on time and as planned, enabling fast and seamless construction.

Thanks to full 3D modeling, Salta Energy visualizes the entire depot before breaking ground: interface points are identified, conflicts resolved, deliveries precisely scheduled, and piping prefabricated in Europe. The result: a smooth, faster construction process, perfectly aligned with the promised budget, timeline, and quality.
Commissioning is the final and most critical step — where everything comes together. Versatile and responsive, the Salta Energy team safely completed the gassing-up and start-up of the installation in just three weeks. The result: an operational depot, ready to receive its first vessel right on schedule. Yet another proof of our ability to handle everything, from the first study to the final turn of the key.

Once the center is operational, Salta Energy remains by your side with its Procure and Procare services. Our goal: to ensure the long-term performance, reliability, and durability of your installation.

Need tailored support for your project?

Nos autres références

Ivory Coast, Daloa
ORYX ENERGIES - An inland filling plant to supply every home

Building a complete LPG filling plant, from A to Z, requires extensive coordination. SALTA ENERGY…

France, Villeneuve-sur-Yonne
Air Liquide - Renovating the only Kyrene filling line in France

SALTA ENERGY is keen to get involved, however big or small your facility is. We can help the…

Tanzania, Dar-Es-Salaam
Oryx Energies - Revamping of the country’s largest oil depots

A SCADA system ensures real-time monitoring and efficient management of operations, ensuring the…

Algeria, Bordj Menaiel
NAFTAL - Algeria’s planned filling plant project relaunched

Abandoning a project can mean losing an investment, or incur risks entailing heavy responsibilities…

Uganda, Kampala
Oryx Energies - The first container center to explore a new market

SALTA ENERGY has the solution for any Customer who wants to conquer a new market in a country where…

Benin, Seme
Oryx Energies - The first cylinder revalidation plant in Benin

LPG cylinders have to be re-tested after 5 years. Thanks to SALTA ENERGY’s studies and equipment…